Reaffirmation of Accreditation Timeline: 2004-2009
|
Date
|
Event/Project |
October 2004 |
President appoints SACS Leadership Team. Provost appoints Chairs of the Compliance Certification Committee and the Quality Enhancement Plan Committee. |
November 2004 |
SACS Compliance Certification Committee Reviews Core Requirements and Comprehensive Standards. |
February 15, 2005 |
RBC establishes SACS-RBC homepage link. |
April 15, 2005 |
Chairs of Audit Committees submit reports to PARC. |
May - August 2005 |
PARC reviews Comprehensive Standards audits and prepares analysis for Steering Committee approval. |
August 2005 |
Provost presents audit update to the campus. Compliance Certification Chair and SACS Reaffirmation Process Chair provide update to campus community. QEP Chair informs campus community on the purpose and elements of a Quality Enhancement Plan. Steering Committee approves PARC audit report. |
September 2005 |
Academic Divisions and Administrative Units review Compliance Certification findings and identify strategies to address deficiencies, weaknesses and recommendations. |
December 2005 |
Chair of the Quality Enhancement Plan Committee returns from SACS Conference in Atlanta and reports findings to PARC. |
January 2006 - February 2007 |
Divisions and Administrative Units implement changes or pilot projects, based upon audit recommendations and/or compliance issues. The Provost appoints a QEP Committee. |
February 2006 |
QEP Kickoff begins. The QEP Committee initiates campus-wide discussions on QEP topics. |
March 2006 |
Establish a SACS budget. |
August 2006 - December 2007 |
Begin writing Compliance Certification Report to encompass the period Spring 2006 through Spring 2007. |
August 8, 2006 |
PARC meets with SACS Chair and Assessment Director of Christopher Newport University. |
September 2006 |
Conduct survey and host discussions with faculty and staff over final candidates for QEP. |
October 2006 |
QEP Committee presents its recommendations for a QEP topic to the Steering Committee. |
November 2006 |
The Steering Committee presents the QEP topic to the President for approval. |
November 2006 - February 2007 |
QEPDC researches areas for QEP concentration. |
November 2006 - April 2007 |
QEP Chair and Provost discuss budgetary implications of the QEP topic. |
December 9-12, 2006 |
Members of PARC attend the SACS Conference in Orlando. |
January 2007 |
Members of the RBC SACS Leadership Team travel to Atlanta for a consultation and orientation workshop; return with recommendations for adjustments to the Compliance Certification and the QEP. |
February 2007 |
Divisions and Units assess all changes and recommend further modifications to original goals and objectives developed in response to the previously identified weaknesses or deficiencies within Core Requirements or Comprehensive Standards as identified in the audit. Representatives from QEPDC travel to Texas to attend the 26th Annual Conference on First Year Experience. Submit biennial budget recommendation to Dean of Administration and Finance. QEP Chair attends national conference on First Year Experience in Dallas. |
March 2007 |
QEPDC identifies and prioritizes major components of the QEP topic, including pilot projects, and engages relevant members of the campus community. |
April 2007 |
QEPDC constructs detailed QEP topic outline with budget and resource implications and presents it to Steering Committee for approval. QEP Chair hosts campus participation in national online conference on "Academic Career Advising." |
May 2007 |
President approves QEP outline. |
May 2007 - February 2008 |
Affected areas develop specific QEP strategies and integrate those into the strategic plan, annual planning priorities and assessment processes. QEP Chair and Provost discuss budgetary implications of the QEP. |
August 2007 |
Present QEP outline to campus community. Candidate for "Lead Evaluator for the QEP" is identified and confirmed. |
August 2007 - May 2008 |
Divisions and Administrative Units plan changes, gather additional baseline data and review appropriate assessment results, or implement pilot projects based upon the QEP outline. |
December 2007 |
Members of PARC attend SACS Conference in New Orleans. |
December 2007 - March 2008 |
Compliance Certification Report is submitted to Steering Committee for approval. Beta test electronic components of the Compliance Certification Report. Steering Committee recommends final Compliance Certification Report to the Leadership Team. Leadership Team approves Compliance Certification Report and sends to President for approval. |
March 2008 |
Compliance Certification (on Core Requirements and Comprehensive Standards) is due. |
April 2, 2008 |
Abstract of QEP is due to SACS. |
May 2008 |
Off-campus SACS team reviews the Compliance Certification. President approves the QEP document. |
June 2008 |
Review final draft of QEP report. |
June 30, 2008 |
Lead Evaluator for the QEP Nomination Form due to SACS. |
August 2008 |
QEP is due. |
August 15, 2008 |
Focused Report is completed, if necessary. |
September 2008 |
Host on-campus SACS site visit. |
November 2008 |
Respond to recommendations in the reaffirmation report, if any. |
June 2009 |
SACS reaffirmation decision is announced. |